STP&I Public Company Limited informed the SET that the company has signed contracts as per details below; The supplement of existing contract and extension of completion date: Project type: Petrochemical Industry; The employer: Tecnicas Reunidas; Scope of work: Module Fabrication & Assembly (Supplement); Period of Contract: July 2019 - August 2021 extended to end at November 2023. The 2 new contracts of an Employer (Not Disclosed the Name) which details are as follows: Project type: Wellhead Platform Decommissioning. Scope of work: Dismantling of Jacket.

Period of Contract: February 2022 - September 2025. Project type: Wellhead Platform Decommissioning. Scope of work: Storage and Refurbishment of Reuse Topside.

Period of Contract: February 2022 - February 2027. Total aggregated contract value of the supplement of existing contract and 2 new projects amount to approximately THB 1,300 Million.