2Q23 RESULTS PRESENTATION

August 04th, 2023

2

2Q23 Highlights

GROWTH

  • 99% of Tucano Wind Complex executed
  • 97% of Cajuína Phase1 Wind Complex executed and 63% of Cajuína Phase 2

OPERATIONAL

  • +1.4 p.p. increase in wind assets availability and +2.9 p.p. increase in solar
  • +62% energy generated, driven by the new wind complexes

FINANCIAL

  • +46% in Net Margin (BRL 515 million) and +45% in EBITDA (BRL 348 million)
  • Operating cash flow of BRL 370 million

Tucano Wind Complex

AGENDA

Growth

Operational

Results

Conclusion and Q&A

4

Tucano generation reaches 216 GWh in 1H23

Tucano - BA (322 MW)

52/52

50/52

48/52

35/52

Complete

Ready for

Commissioned

Structure

Commissioning

Operational

Energy Generated

Civil

99%

(GWh)

63

Substation

100%

49

Transmission Line

2%100%

38

Connection Bay

100%

28

25

WTGs

25%99%

Project 99% completed¹

Mar-23

Apr-23

May-23

Jun-23

Jul-23

1 - Based on the physical-financial curve (incurred capex on the total project capex, weighted by the physical progress schedule of the project).

Tucano Wind Complex

5

Completion of construction works adds +314 MW of capacity in 2H23

Cajuína Phase 1 - RN (314 MW)

Civil

99%

Substation (Caju)

99%

Transmission Line

100%

2%

Connection Bay

100%

WTGs

92%

Project

97%

Completed¹

20/55

55/55

44/55

20/55

Complete

Ready for

Commissioned

Operational

structure

Commissioning

The start of the test operations

generates +33 GWh of energy in 2Q23

Cajuína Wind Complex

1 - Based on the physical-financial curve (incurred capex on the total project capex, weighted by the physical progress schedule of the project).