Fresnillo plc 21 Upper Brook Street London W1K 7PY United Kingdom www.fresnilloplc.com

24 April 2024

FIRST QUARTER PRODUCTION REPORT

FOR THE THREE MONTHS ENDED 31 MARCH 2024

Octavio Alvídrez, Chief Executive Officer, said:

"We have started the year with our performance in line with our expectations. Silver production was slightly up over the same quarter last year, driven by the contribution of Juanicipio, higher grades at San Julián Veins and a stronger performance at Saucito. Gold production was slightly lower as expected, due mainly to the lower output from the Noche Buena mine as it approaches its end of life and the lower grade at Herradura in line with the mine plan. We continue to prioritise safety across all our operations in 2024, while also focusing on reducing costs, improving efficiencies at all mine sites, and with our newest Juanicipio mine now fully ramped up, on the advancement of our growth pipeline. Our guidance for the full year is unchanged."

HIGHLIGHTS

Silver

  • Quarterly attributable silver production of 13.5 moz (including Silverstream) decreased 4.6% vs. 4Q23 due to the lower ore grade and, to a lesser extent, decreased volume of ore processed at San Julián (DOB), and lower ore grade at Saucito and Fresnillo, mitigated by the higher ore grade at San Julián Veins.
  • Quarterly attributable silver production (including Silverstream) increased 2.7% vs. 1Q23, primarily due to the increased contribution from Juanicipio, the higher ore grade at San Julián Veins and increased volume of ore processed at Saucito, partly offset by the lower ore grade and volume of ore processed at Fresnillo and San Julián (DOB).

Gold

  • Quarterly attributable gold production of 140.8 koz, down 7.7% vs. 4Q23, mainly driven by the lower ore grade at Herradura in line with the mine plan, and the mine closure plan at Noche Buena, partly mitigated by the higher ore grade at Saucito.
  • Quarterly attributable gold production down 18.6% vs. 1Q23 primarily due to the lower volume of ore processed at Herradura and the mine closure plan at Noche Buena, partly mitigated by the increased contribution from Juanicipio.

By-Products

  • Quarterly attributable by-product lead production down 6.1% vs. 4Q23 primarily due to the lower ore grade at Saucito and lower ore grade, decreased volume of ore processed and lower recovery rate at San Julián (DOB), partly mitigated by the higher ore grade and recovery rate at Fresnillo.

1

  • Quarterly attributable by-product lead production up 11.6% vs. 1Q23 due to the increased contribution from Juanicipio and the higher volume of ore processed at Saucito, partly offset by the lower ore grade, volume of ore processed and recovery rate at San Julián (DOB).
  • Quarterly attributable by-product zinc production down 9.3% vs. 4Q23 mainly due to the lower ore grade at Saucito, partly mitigated by the higher ore grade at Fresnillo.
  • Quarterly attributable by-product zinc production up 8.5% vs. 1Q23 due to the increased contribution from Juanicipio and the higher volume of ore processed at Saucito, partly offset by the lower ore grade and volume of ore processed at San Julián (DOB) and decreased volume of ore processed at Fresnillo.

1Q24

4Q23

% Change

1Q23

% Change

Silver (koz)

13,117

13,548

(3.2)

12,337

6.3

Silverstream (koz)

397

612

(35.1)

821

(51.6)

Total Silver (koz)

13,513

14,161

(4.6)

13,158

2.7

Gold (oz)

140,847

152,605

(7.7)

173,034

(18.6)

Lead (t)

14,924

15,895

(6.1)

13,368

11.6

Zinc (t)

26,157

28,844

(9.3)

24,118

8.5

SAFETY PERFORMANCE

As already reported in the Preliminary Results, we were deeply saddened to confirm a fatal accident at the Fresnillo mine in January. A thorough investigation of the incident was carried out, together with the authorities, to identify the root cause and implement corrective actions. The safety of our people, and the installation of a true safety culture across all our operations for both employees and contractors, remains the absolute priority for the Group.

2024 OUTLOOK

Our 2024 outlook is in line with previous expectations:

  • Attributable silver production expected to be in the range of 55.0 to 62.0 moz (including Silverstream)
  • Attributable gold production expected to be in the range of 580 to 630 koz.

Expressed in silver equivalent ounces1, total production is expected to be 101-112 million ounces.

For further information, please visit our website www.fresnilloplc.comor contact:

FRESNILLO PLC

Tel: +44

(0)20 7399 2470

London Office

Gabriela Mayor, Head of Investor Relations

Mark Mochalski

Mexico City Office

Tel: +52

55 52 79 3206

Ana Belem Zárate

POWERSCOURT

Tel: +44

(0)7793 858 211

Peter Ogden

1 Au:Ag ratio of 80:1

2

MINING OPERATIONS

FRESNILLO MINE PRODUCTION

1Q24

4Q23

% Change

1Q23

% Change

Ore Processed (t)

622,390

609,135

2.2

668,366

(6.9)

Production

Silver (koz)

2,676

2,781

(3.8)

3,557

(24.8)

Gold (oz)

9,846

8,149

20.8

8,750

12.5

Lead (t)

6,191

5,226

18.5

5,651

9.6

Zinc (t)

11,668

10,592

10.2

12,094

(3.5)

Ore Grades

Silver (g/t)

151

160

(5.6)

184

(17.9)

Gold (g/t)

0.66

0.59

11.9

0.57

15.8

Lead (%)

1.15

1.03

11.7

1.00

15.0

Zinc (%)

2.58

2.42

6.6

2.42

6.6

Quarterly silver production decreased 3.8% when compared to 4Q23, mainly driven by the higher proportion of volumes extracted from the western areas of the mine with lower silver ore grade but higher gold and base metal contents, the temporary operating constraints in the eastern areas, including ground conditions and delays in mine infrastructure and, to a lesser extent, variations with the geological model. This was partly mitigated by the increased volume of ore processed from these areas.

Quarterly silver production decreased 24.8% vs. 1Q23, mainly due to the lower ore grade as explained above and lower volume of ore processed in accordance with the mine plan.

Mine development rates remained stable at an average of 3,027m per month in 1Q24 (4Q23: 3,038m per month).

Quarterly by-product gold production increased 20.8% and 12.5% vs. 4Q23 and 1Q23, respectively driven by the higher ore grade and increased recovery rate.

Silver ore grade in 2024 has been reviewed and is expected to be in the range of 160 to 180 g/t, while the gold ore grade is estimated to be between 0.60 to 0.70 g/t.

SAUCITO MINE PRODUCTION

1Q24

4Q23

% Change

1Q23

% Change

Ore Processed (t)

574,969

576,189

(0.2)

471,959

21.8

Production

Silver (koz)

3,234

3,399

(4.9)

2,804

15.3

Gold (oz)

19,343

17,256

12.1

21,378

(9.5)

Lead (t)

4,908

6,311

(22.2)

4,301

14.1

Zinc (t)

6,694

10,335

(35.2)

5,991

11.7

Ore Grades

Silver (g/t)

198

204

(2.9)

207

(4.3)

Gold (g/t)

1.35

1.20

12.5

1.77

(23.7)

Lead (%)

1.00

1.27

(21.3)

1.07

(6.5)

Zinc (%)

1.52

2.29

(33.6)

1.68

(9.5)

3

Quarterly silver production decreased 4.9% vs. 4Q23 mainly driven by the lower ore grade which resulted from: i) additional ground support required in some areas with higher silver ore grade, and ii) a slight increase in dilution, primarily in stopes mined through the long hole drilling method. Both factors were addressed in early March by increasing ground support and adjusting the drilling and blasting patterns, which will improve the silver grade going forward.

Quarterly silver production increased 15.3% vs. 1Q23 primarily due to the higher volume of ore processed as a result of the improved productivity and increased equipment availability. This more than compensated for the lower ore grade driven by the previously mentioned factors.

Quarterly by-product gold production increased 12.1% vs. 4Q23 mainly driven by the higher ore grade.

Quarterly by-product gold production decreased 9.5% vs. 1Q23 driven by the lower ore grade as a result of higher dilution and to a lesser extent lower recovery rate, partly mitigated by the higher volumes of ore processed due to previously mentioned factors.

Mine development rates remained stable quarter on quarter at 2,840m per month in 1Q24 (4Q23: 2,810m per month), in accordance with the plan.

The silver ore grade for 2024 is expected to be in the range of 200-220 g/t, while the gold grade is estimated to be between 1.10-1.30 g/t.

PYRITES PLANT

1Q24*

4Q23*

% Change

1Q23

% Change

Pyrite Concentrates Processed (t)

36,344

48,167

(24.5)

27,952

30.0

Production

Silver (koz)

356

328

8.5

111

220.7

Gold (oz)

628

599

4.8

270

132.6

Ore Grades

Silver (g/t)

497

331

50.2

177

180.8

Gold (g/t)

2.15

1.71

25.7

1.31

64.1

*Includes concentrates of Fe from Saucito and Fresnillo.

CIÉNEGA MINE PRODUCTION

1Q24

4Q23

% Change

1Q23

% Change

Ore Processed (t)

261,681

292,612

(10.6)

240,148

9.0

Production

Gold (oz)

10,688

9,187

16.3

9,302

14.9

Silver (koz)

1,201

1,213

(1.0)

980

22.6

Lead (t)

652

693

(5.9)

748

(12.8)

Zinc (t)

832

723

15.1

1,002

(17.0)

Ore Grades

Gold (g/t)

1.38

1.07

29.0

1.30

6.2

Silver (g/t)

166

151

9.9

147

12.9

Lead (%)

0.40

0.39

2.6

0.47

(14.9)

Zinc (%)

0.59

0.47

25.5

0.77

(23.4)

4

Quarterly gold production increased 16.3% vs. 4Q23 mainly due to the higher ore grade from the Virginia stope. This was partly offset by the lower volume of ore processed due to power outages in March.

Quarterly gold and silver production increased 14.9% and 22.6% vs. 1Q23 respectively, due to the increased volume of ore processed as a result of the timely preparation of stopes at the Taspana and Veta Nueva areas, and the higher ore grade from new stopes at the Jessica, Gota and Gotita areas.

Quarterly silver production slightly decreased vs. 4Q23 driven by the lower volume of ore processed as mentioned above, partly offset by the higher ore grade.

The gold and silver ore grades for 2024 are estimated to be in the ranges of 1.1-1.3 g/t and 160-180 g/t respectively.

SAN JULIÁN MINE PRODUCTION

1Q24

4Q23

% Change

1Q23

% Change

Ore Processed Veins (t)

291,003

291,661

(0.2)

283,752

2.6

Ore Processed DOB (t)

501,434

525,081

(4.5)

522,260

(4.0)

Total production at San Julián

Gold (oz)

12,582

11,034

14.0

12,033

4.6

Silver (koz)

3,039

3,156

(3.7)

3,412

(10.9)

Production Veins

Gold (oz)

11,973

10,117

18.3

11,139

7.5

Silver (koz)

2,039

1,719

18.6

1,312

55.4

Production DOB

Gold (oz)

609

918

(33.7)

894

(31.9)

Silver (koz)

1,000

1,437

(30.4)

2,100

(52.4)

Lead (t)

962

1,332

(27.8)

1,855

(48.1)

Zinc (t)

3,241

3,362

(3.6)

3,755

(13.7)

Ore Grades Veins

Gold (g/t)

1.35

1.13

19.5

1.28

5.5

Silver (g/t)

239

200

19.5

158

51.3

Ore Grades DOB

Gold (g/t)

0.06

0.08

(25.0)

0.09

(33.3)

Silver (g/t)

74

100

(26.0)

146

(49.3)

Lead (%)

0.26

0.33

(21.2)

0.46

(43.5)

Zinc (%)

0.89

0.86

3.5

0.96

(7.3)

SAN JULIÁN VEINS

Quarterly silver production increased 18.6% vs. 4Q23 and 55.4% vs. 1Q23, mainly due to the higher ore grade at San Antonio, La Dura and Eliza veins and increased volumes of development ore with high ore grade.

Quarterly gold production increased 18.3% vs. 4Q23 mainly driven by the higher ore grade due to the aforementioned factors.

5

Quarterly gold production increased 7.5% vs. 1Q23 mainly due to the higher ore grade and, to a lesser extent, the increased volume of ore processed driven by the optimisation of the maintenance programme.

We expect the 2024 silver and gold ore grades to be in the ranges of 160-180 g/t and 1.00-1.20 g/t, respectively.

SAN JULIÁN DISSEMINATED ORE BODY (DOB)

Quarterly silver production decreased vs. 4Q23 and 1Q23 mainly as a result of lower ore grade in the periphery of the ore body and the decrease in volumes of ore processed as the mine approaches the end of its life.

The mine plan of the disseminated ore body was reviewed due to ground instability in some of the remaining production areas. As a result, some changes to the mine plan have been made, which will have an impact on the average silver ore grade for 2024, which is now expected to be around 70g/t. Mining activities are expected to conclude in 3Q24. The impact on production at San Julián DOB has been partly offset by a better performance in San Julián Veins, as previously described.

HERRADURA TOTAL MINE PRODUCTION

1Q24

4Q23

% Change

1Q23

% Change

Ore Processed (t)

4,695,531

4,534,745

3.5

6,485,710

(27.6)

Total Volume Hauled (t)

22,140,776

24,409,823

(9.3)

29,223,867

(24.2)

Production

Gold (oz)

78,058

93,432

(16.5)

106,832

(26.9)

Silver (koz)

119

147

(19.0)

208

(42.8)

Ore Grades

Gold (g/t)

0.67

0.84

(20.2)

0.73

(8.2)

Silver (g/t)

1.32

1.69

(21.9)

1.72

(23.3)

Quarterly gold production decreased 16.5% vs. 4Q23 mainly driven by the lower ore grade, in accordance with the mine plan. This was partly offset by the increase in volume of ore processed driven by better performance at the dynamic leaching plants in 1Q24, which had been impacted by the previously reported electrical fault in the third and fourth quarters of 2023.

Quarterly gold production decreased 26.9% vs. 1Q23 primarily due to the lower volume of ore processed as a result of heavy rain in March, which required additional pumping at the bottom of the pit, and consequently disrupted mining activities. Additionally, the lower ore grade also contributed to the decreased gold production.

The gold ore grade in 2024 is expected to be in the range of 0.60-0.70 g/t.

NOCHE BUENA

4,144 ounces of gold were recovered from the leaching pads at Noche Buena during the quarter. As previously reported, mining activities concluded in May 2023, and the closure plan is ongoing at this mine.

6

JUANICIPIO - ATTRIBUTABLE ORE PROCESSED AND PRODUCTION

1Q24

4Q23*

% Change

1Q23**

% Change

Ore Processed (t)

182,383

194,189

(6.1)

124,333

46.7

Production

Silver (koz)

2,489

2,523

(1.3)

1,260

97.5

Gold (oz)

5,559

5,931

(6.3)

3,392

63.9

Lead (t)

2,211

2,334

(5.3)

813

172.0

Zinc (t)

3,722

3,832

(2.9)

1,275

191.9

Ore Grades

Silver (g/t)

476

467

1.9

363

31.1

Gold (g/t)

1.32

1.37

(3.6)

1.08

22.2

Lead (%)

1.35

1.35

0.0

0.74

82.4

Zinc (%)

2.49

2.44

2.0

1.44

72.9

  • Includes ore processed at the Fresnillo and Saucito beneficiation plants.
  • Includes ore processed from initial tests during the commissioning of the Juanicipio plant and ore processed at the Fresnillo and Saucito beneficiation plants.

Attributable quarterly silver production decreased vs. 4Q23 primarily driven by the lower volume of ore processed due to a minor maintenance stoppage of four days, originally planned for two, in March. This was partly offset by the higher ore grade and increased recovery rates.

Attributable quarterly silver and gold production increased significantly vs. 1Q23 as commissioning of the flotation plant concluded in 1Q23.

Attributable quarterly gold production decreased 6.3% vs. 4Q23 mainly due to the lower volume of ore processed.

The silver ore grade for 2024 is expected to be in the range of 380-420 g/t.

SILVERSTREAM

Quarterly silverstream production decreased 35.1% and 51.6% vs. 4Q23 and 1Q23 mainly due to the decrease in volumes of ore processed driven by a technical stoppage of the flotation plant, and a lower ore grade. The maintenance programme was concluded in April.

Silver production in 2024 is estimated to be in the range of 2.5-3.0 moz.

ABOUT FRESNILLO PLC

Fresnillo plc is the world's largest primary silver producer and Mexico's largest gold producer, listed on the London and Mexican Stock Exchanges under the symbol FRES.

Fresnillo plc has eight operating mines, all of them in Mexico - Fresnillo, Saucito, Juanicipio, Ciénega, Herradura, Soledad-Dipolos1, Noche Buena and San Julián (Veins and Disseminated Ore Body) and four advanced exploration projects - Orisyvo, Rodeo, Guanajuato and Tajitos as well as a number of other long term exploration prospects.

Fresnillo plc has mining concessions and exploration projects in Mexico, Peru and Chile.

Fresnillo plc's goal is to maintain the Group's position as the world's largest primary silver company and Mexico's largest gold producer.

1 Operations at Soledad-Dipolos are currently suspended.

7

FORWARD-LOOKING STATEMENTS

Information contained in this announcement may include 'forward-looking statements'. All statements other than statements of historical facts included herein, including, without limitation, those regarding the Fresnillo Group's intentions, beliefs or current expectations concerning, amongst other things, the Fresnillo Group's results of operations, financial position, liquidity, prospects, growth, strategies and the silver and gold industries are forward- looking statements. Such forward-looking statements involve risk and uncertainty because they relate to future events and circumstances. Forward-looking statements are not guarantees of future performance and the actual results of the Fresnillo Group's operations, financial position and liquidity, and the development of the markets and the industry in which the Fresnillo Group operates, may differ materially from those described in, or suggested by, the forward- looking statements contained in this document. In addition, even if the results of operations, financial position and liquidity, and the development of the markets and the industry in which the Fresnillo Group operates are consistent with the forward-looking statements contained in this document, those results or developments may not be indicative of results or developments in subsequent periods. A number of factors could cause results and developments to differ materially from those expressed or implied by the forward-looking statements including, without limitation, general economic and business conditions, industry trends, competition, commodity prices, changes in regulation, currency fluctuations (including the US dollar and Mexican Peso exchanges rates), the Fresnillo Group's ability to recover its reserves or develop new reserves, including its ability to convert its resources into reserves and its mineral potential into resources or reserves, changes in its business strategy and political and economic uncertainty.

8

Fresnillo plc 21 Upper Brook Street Londres W1K 7PY Reino Unido www.fresnilloplc.com

24 de Abril de 2024

REPORTE DE OPERACIONES AL 31 DE MARZO DE 2024

Octavio Alvídrez, Director General, comentó:

"Hemos comenzado el año con un rendimiento acorde con nuestras expectativas. La producción de plata aumentó ligeramente con respecto al mismo trimestre del año pasado, impulsada por la contribución de Juanicipio, mayores leyes en San Julián Vetas y un desempeño más sólido en Saucito. La producción de oro fue ligeramente inferior de acuerdo a lo esperado, debido principalmente a la menor producción de la mina Noche Buena a medida que se acerca al final de su vida útil y a la menor ley en Herradura en línea con el plan de minado. Continuamos priorizando la seguridad en todas nuestras operaciones en 2024, al mismo tiempo que nos centraremos en la disminución de los costos, mejorando la eficiencia en todas las unidades mineras y, con nuestra nueva mina Juanicipio ahora completamente en operación, sobre el avance de nuestra cartera de negocios. Nuestra guía para todo el año no ha cambiado."

RESUMEN

Plata

  • La producción trimestral de plata atribuible de13.5 moz (incluyendo Silverstream) disminuyó 4.6% en comparación con el 4to Trim23 debido a la menor ley y, en menor medida, a la disminución del volumen de mineral procesado en San Julián (DOB), y menor ley en Saucito y Fresnillo, mitigado por la mayor ley en San Julián Vetas.
  • La producción trimestral de plata atribuible (incluyendo Silverstream) aumentó 2.7% en comparación con el 1er Trim23, principalmente debido a la mayor contribución de Juanicipio, mayor ley de San Julián Vetas y aumentó en el volumen del mineral procesado en Saucito, parcialmente compensado por la menor ley y menor volumen de mineral procesado en Fresnillo y San Julián (DOB).

Oro

  • La producción trimestral atribuible de oro de 140.8 koz disminuyó 7.7% en comparación con el 4to Trim23, impulsado principalmente por la menor ley en Herradura en línea con el plan de minado, y el plan de cierre de la mina en Noche Buena, en parte mitigado por la mayor ley en Saucito.
  • La producción trimestral atribuible de oro disminuyó 18.6% en comparación con el 1er Trim23 principalmente debido al menor volumen de mineral procesado en Herradura y al plan de cierre de la mina en Noche Buena, mitigado en parte por el mayor aporte de Juanicipio.

Sub-Productos

  • La producción trimestral atribuible del sub-producto plomo disminuyó 6.1% en comparación con el 4to Trim23 principalmente debido a la menor ley en Saucito y a la menor ley, la disminución del volumen de mineral procesado y la menor recuperación en San Julián (DOB), mitigado en parte por la mayor ley y la mayor tasa de recuperación a Fresnillo.

1

  • La producción trimestral atribuible del sub-producto plomo incrementó 11.6% en comparación con el 1er Trim23 debido al mayor aporte de Juanicipio y al mayor volumen de mineral procesado en Saucito, compensado parcialmente por la menor ley, menor volumen de mineral procesado y menor recuperación en San Julián (DOB).
  • La producción trimestral atribuible del sub-producto zinc disminuyó 9.3% en comparación con el 4to Trim23 principalmente debido a la menor ley en Saucito, en parte mitigada por la mayor ley en Fresnillo.
  • La producción trimestral atribuible del sub-producto zinc incrementó 8.5% en comparación con el 1er Trim23 debido al mayor aporte de Juanicipio y al mayor volumen de mineral procesado en Saucito, compensado en parte por la menor ley y menor volumen de mineral procesado en San Julián (DOB) y disminución del volumen de mineral procesado a Fresnillo.

1er Trim24

4to Trim23

% Var

1er Trim23

% Var

Plata (koz)

13,117

13,548

(3.2)

12,337

6.3

Silverstream (koz)

397

612

(35.1)

821

(51.6)

Total Plata (koz)

13,513

14,161

(4.6)

13,158

2.7

Oro (oz)

140,847

152,605

(7.7)

173,034

(18.6)

Plomo (t)

14,924

15,895

(6.1)

13,368

11.6

Zinc (t)

26,157

28,844

(9.3)

24,118

8.5

SEGURIDAD

Como ya se informó en los Resultados Preliminares, nos entristeció profundamente confirmar un accidente fatal en la mina Fresnillo en enero. Se llevó a cabo una investigación exhaustiva del incidente, junto con las autoridades, para identificar la causa raíz e implementar acciones correctivas. La seguridad de nuestra gente y la instalación de una verdadera cultura de seguridad en todas nuestras operaciones, tanto para los empleados como para los contratistas, sigue siendo la prioridad absoluta para el Grupo.

PERSPECTIVAS 2024

Nuestros objetivos para 2024 está en línea con las expectativas anteriores:

  • Se espera que la producción atribuible de plata esté en el rango de 55.0 a 62.0 moz (incluyendo Silverstream)
  • Se espera que la producción atribuible de oro esté en el rango de 580 a 630 koz.

Expresada en onzas de plata equivalente1, se espera que la producción total sea de 101 a 112 millones de onzas.

Para obtener más información, visite nuestro sitio web www.fresnilloplc.com o póngase en contacto con:

FRESNILLO PLC

Tel: +44

(0)20 7399 2470

Oficina de Londres

Gabriela Mayor, Jefa de Relaciones con

Inversionistas

Mark Mochalski

Oficina de Ciudad de México

Tel: +52

55 52 79 3206

Ana Belem Zárate

POWERSCOURT

Tel: +44

(0)7793 858 211

1 Relación Au:Ag de 80:1

2

Para continuar a leer este documento, haga clic aquí para la versión original.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Fresnillo plc published this content on 24 April 2024 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 24 April 2024 23:43:04 UTC.