All dollar amounts are expressed in Canadian dollars unless otherwise noted.
A remote presentation for sell-side analysts and investors will be held remotely at
Analysts and investors who wish to participate in the webcast are requested to register via the link here: https://brrmedia.news/AMRQ_FY23
Eldur Olafsson, CEO of Amaroq, commented: 'Following our successful Fundraising in
'We experienced some operational and procurement delays towards the end of 2023 due to adverse weather conditions, which continued into the start of 2024. This situation has now significantly improved and we are making good operational progress.
'
FY 2023 Corporate Highlights
Amaroq group liquidity of
Gold business working capital of
Strategic minerals business available liquidity of
Successful transfer of Icelandic listing to Iceland Nasdaq Main Market in 2023 and admission to the OMX Iceland 15 Index, effective in
Completion of most successful drilling program at Nalunaq to date and discovery of new 75 vein, underpinning potential for faster resource growth
Awarded two additional licences in
Geological interpretation and advanced data science at the Nanoq target have expanded its potential size and have indicated a 25km corridor linking it to the Jokum's Shear project
Promising results from 2023
Post-period, in
Amaroq achieved score of 'Good' by Icelandic ratings agency Reitun it their first ESG assessment of the Company. Amaroq was placed it in category B3, with a score of 68 points. The rating is based on the Company's performance in environmental, social and governance (ESG) matters.
Q4 2023 Operational Highlights
Contracting and Procurement: At the end of Q4 2023, 80% of the key contracts for the processing plant were concluded and procurement was 80% completed.
Engineering: Process plant engineering was 77% complete at the end of Q4 2023 based on the updated project scope
Construction: Two wings were added to the camp, increasing the accommodation capacity by 60 beds. The overall construction status of the processing plant was 16% at the end of Q4 2023 based on the updated project scope and 23% as at the end of
Mining: Mine rehabilitation works were continued in Q4 2023. This work lays the foundation for safe and efficient trial mining to commence at the end of Q1 2024 or early Q2 2024
Nalunaq Exploration: New underground samples beyond the historically mined areas of Target Block, Nalunaq's largest historic mining block, confirmed continuation of high-grade mineralisation into modelled extension area with grades of up to 48.3g/t Au over 1m. Additional intersections of the newly discovered 75 Vein provide further confidence in its thickness and continuity
Nalunaq Project KPIs 45,384 hours worked during Q4 2023. 107,184 total hours worked during FY 2023
Daily average of 33 people working on site at Nalunaq in Q4 2023
One Lost Time Injury (LTI) in 2023
Amaroq remains committed to ensuring local representation among the workforce, with the ratio of Greenlandic personnel at Nalunaq standing at 61% for 2023
2024 Outlook
Permitting: The public consultation for the Environmental Impact Assessment (EIA) and Social Impact Assessment (SIA) for Nalunaq closed on
Engineering: Engineering for the processing plant is expected to be completed in Q2 2024
Contracting and Procurement: The remaining contracts are expected to be concluded in Q2 2024. The only outstanding major contract is the installation of the processing plant components. The quotes of different bidders are currently being evaluated and the contract will then be awarded
Construction: Placement of the process plant foundations is nearing completion. The erection of the steel structure of the process plant building is expected to commence in
Mining: The rehabilitation of the ramp from the 300 level portal to the Mountain Block is nearing completion and will be followed by the development of a ramp extending higher up into the Mountain Block. Rehabilitation of the mine will progress based on the location of future planned mining activities. The Company expects to mine first gold in 2024 and plans to provide a progress update with timings for guidance for the project at an investor event in
Support Infrastructure: In 2024 additional containers will be added, which will allow Amaroq to accommodate in total up to 120 persons
Nalunaq Exploration: Underground focused exploration will continue to target extension of the Mountain and Target Blocks as well as further delineating the newly discovered 75 Vein
2024 Operational Workplan
Nalunaq Development Workplan
Nalunaq
The main ramp will be developed from 720 level upwards into the Mountain Block. Starting from the ramp, crosscuts will be driven into the main vein at different levels and then drifts will be developed following the strike of the vein. At a later stage the ore between these ore drifts will be mined using the long-hole stoping method. Later in 2024, development and exploration drilling activities will be carried out in the Target Block in parallel to the aforementioned works. Rehabilitation of the mine will continue depending on the locations, where future mining activities are planned.
Gold Exploration Projects
Nalunaq
Following the underground rehabilitation, exploration will now switch to underground drilling to target continued extensions of both the Mountain and Target Blocks while simultaneously targeting further intersections into the 75 vein.
Nanoq
Following the expansion of the mineral potential at Nanoq in 2023, the Company will construct facilities and finalise exploration plans allowing Amaroq the option to conduct a maiden core drilling programme across the first target at Nanoq. In addition, ground studies will be conducted to further establish the additional targets generated by the geophysical and modelling work completed in 2023.
Vagar and Surrounding Areas
Amaroq intends to conduct a target generation programme across the Vagar licence, including
Strategic Minerals Projects (Amaroq 51%)
Exploration at Target West will concentrate on further defining Unit 1, which hosts observed copper mineralisation. Mapping, sampling and a limited drilling programme will look to expand the footprint of Unit 1 and test for higher grade material at depth.
Target generation programmes will continue across Sava, North Sava and the full extent of the Copper Belt assessing high priority porphyry and IOCG targets on the ground. The aim of this programme will be to define new areas for scout drilling.
Stendalen
Following the new Ni-Cu discovery made at Stendalen, Amaroq intends to mobilise three drill rigs and a semi-permanent camp to site to facilitate an expanded drilling programme. Drilling will focus on intersecting further target areas at the base of the Stendalen intrusion including the interpreted
The Company plans to conduct further ground geophysics to provide further confidence to the overall extend and geometry of the intrusion and associated sulphide mineralisation.
Leveraging off the data from this discovery, ground studies will also assess the potential for further target areas with Stendalen and more regionally.
Kobberminebugt
Amaroq will continue to review the results of the detailed geophysical programme conducted over the Kobberminebugt licence in 2023. Specific geophysical targets will be followed up in the field with detailed mapping and surface sampling ahead of defining more definitive targets for future scout drilling.
Nunarsuit
Geophysical data collected during 2023 is currently being fully assessed and Amaroq aim to conduct a targeted field programme on the licence during the summer of 2024. Initial targets will include specific geophysical anomalies as well as outcropping niobium bearing pegmatites.
Contact:
Eldur Olafsson
Executive Director and CEO
Email: eo@amaroqminerals.com
Tel: +44 (0)7713 126727
Email: ew@amaroqminerals.com
Simon Mensley
Tel: +44 (0) 20 7710 7600
About
Certain statements in this release constitute 'forward-looking statements' or 'forward-looking information' within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as 'may', 'would', 'could', 'will', 'intend', 'expect', 'believe', 'plan', 'anticipate', 'estimate', 'scheduled', 'forecast', 'predict' and other similar terminology, or state that certain actions, events or results 'may', 'could', 'would', 'might' or 'will' be taken, occur or be achieved. These statements reflect the Company's current expectations regarding future events, performance and results and speak only as of the date of this release.
Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to: material adverse changes, unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices and the failure of exploration, refurbishment, development or mining programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.