The Solar Gard roofing project is being managed by McKay Roofing and the
This project involves the installation of a coating system over the existing roofing material. The new coating system is Title 24 compliant and has a 20-year lifespan. This project involves a 2-part process where the first coat covers the roof, and the second coat applies an acrylic coating with granules. This makes the roof safe for pedestrians to walk across when they need to access the roof for mechanical maintenance. The project should wrap up in 6-8 weeks, weather permitting.
Overview of roof area to be coated.
Roof before first coat (left) and roof after first coat (right).
As mentioned in previous releases, the first phase of
During phase 2, the scope of work includes performing the required saw cutting, trenching, backfilling and surfacing of the impacted lot by restoring to its original condition. In addition, this phase includes the installation of and electrically connecting the EV infrastructure by incorporating the wiring devices and all necessary associated components for a fully functional system including testing of the chargers.
To date, trenching and conduit is complete with asphalt roughly 90% completed. In addition, the wall construction which houses the 2 transformers, 3 disconnects and one panel is anticipated to be completed the first week of March with the overall project being completed mid-June.
Trenching during (left) and after (right) with conduit and wiring in place.
Bollards installed and ready for EV Charging Stations. Installation of stations will begin once transformers and panels are completed.
About
Press Release Contact:
jbrehm@sircfamily.com
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/f81585e2-d3d7-4c39-8465-8769755e08df
https://www.globenewswire.com/NewsRoom/AttachmentNg/cb5eb9ab-da68-4ede-832d-032966ba655c
https://www.globenewswire.com/NewsRoom/AttachmentNg/3358f7b6-f7cb-42b6-8def-7fbeacb2df20
https://www.globenewswire.com/NewsRoom/AttachmentNg/a52566cd-3b67-427b-a46b-d9ebe2f99200
Overview of roof area
to be coated
Roof before first coat (left)
and roof after first coat (right).
Trenching during (left) and after (right) with conduit and wiring in place.
Foundation for EV Charging Stations in progress.
Bollards installed and ready for EV Charging Stations.
Installation of stations will begin once transformers and panels are completed.