By the results of 5 months of the current year IDGC of the South (Rosseti group) has fulfilled the planned volume of repair works on various facilities by 111%.

Starting this year power engineers of IDGC of the South has completed overhaul of 21 substations of 35-110kV, repaired around 3.6 thousand kilometres of power lines and 692 transformer stations of 6/10-0.4kV. Also 336 hectares of power line routes were cleared from trees and vegetation.

The company spent around 360 million rubles for repair works, which is 33% of the annual repair programme and 115% of the current plan.

The Rostov branch fulfills its repair programme according of the schedule. Specialists from Kalmenergo have exceeded the plan of works at transformer stations and power lines. The Volgograd branch has over-fulfilled the plan of works on trees trimming and removing vegetation around power lines. In Astrakhan our specialists did great job on repair of transformer stations.

Implementation of repair programme in full volume will ensure the company is ready to autumn-winter period and is able provide reliable power supply.