Subject:

Notification of a Contract Signing for Construction and renovation of Nonsi power station, Prachinburi

Province, According to the Transmission and Distribution System Development Project, phase 2, plan 2

via e-bidding from Provincial Electricity Authority

Attention : Directors and Managers

The Stock Exchange of Thailand

Interlink Communication Public Company Limited (ILINK) (the "Company") has joined with Interlink Power and Engineering Company Limited (Subsidiary company) under the name of " INTERLINK CONSORTIUM " would like to inform that " INTERLINK CONSORTIUM " has signed the Contract for Construction and renovation of Nonsi power station, Prachinburi Province, According to the Transmission and Distribution System Development Project, phase 2, plan 2 via e-biddingNo. TDDP2-NSI/2565on July 25, 2022 with the Provincial Electricity Authority, the contract details are as follows;

Scope of work

: Construction and renovation of Nonsi power station, Prachinburi Province, According to the

Transmission and Distribution System Development Project, phase 2, plan 2, totaling 1 job.

Contract Value

: Baht 314,800,000 (three hundred fourteen million eight hundred thousand baht)

VAT included.

Period of Delivery

: 510 days after receiving a notification letter from the Provincial Electricity Authority

to start working.

To thoroughly communicate this information to investors, we would like to disclose aforementioned information through SET.

Please be informed accordingly.

Yours sincerely,

(Mr. Sombat Anuntarumporn)

Chairman

Attachments