Continental Gold Inc. provided a project update for its Buriticá project in northwestern Antioquia, Colombia. Construction of the project remains on schedule for mechanical completion in First Quarter 2020, ramping to commercial production approximately six to nine months thereafter. Mill facilities construction was 88% completed as of October 31, 2019. Major milling equipment installation has been completed with piping, electrical and instrumentation advancing well. Acceleration of underground development continues; Continental's mine crews achieved over 1.5 kilometres of lateral development in October, the highest monthly advance to-date. Total lateral development advance is 19,800 metres, including ramps, sublevels and ore development. Pre-production stockpile of 81,200 tonnes averaged 7.2 g/t gold at the end of October 2019 and is anticipated to continue increasing by approximately 10,000-15,000 tonnes per month. The 110-kV powerline construction was completed in Third Quarter 2019, with line and mine substation energization in November.