All amounts herein are reported in $000s of Canadian dollars (“C$”) unless otherwise specified.
Q1 2024 AND RECENT HIGHLIGHTS
- On
May 7, 2024 , the Company announced a$5,000 non-brokered flow through private placement (the “Offering”), the proceeds of which will be used to fund the 2024 exploration program at the PGP. The Offering will consist of 6,024,096 common shares of the Company, which qualify as "flow-through shares" within the meaning of the Income Tax Act (Canada ) (the “FT Shares”), at a price of$0.83 per FT Share. The closing of the Offering is expected to occur in one or more tranches in or around late-May tomid-June 2024 , and is subject to certain conditions including, but not limited to, the receipt of all necessary regulatory approvals, including the acceptance of theToronto Stock Exchange . - Rock was introduced into the grinding circuit of the mill on
March 31, 2024 , and first gold-bearing ore was introduced to the mills onApril 5, 2024 . OnApril 20, 2024 , first gold was poured as a part of the commissioning process. Commissioning of the processing plant at PGP is ongoing, with commercial production anticipated in Q3 2024. Two gold pours have been completed using gold recovered from the gravity circuit. Another pour from gold recovered from the carbon-in-leach (“CIL”) circuit is anticipated imminently. - On
February 20, 2024 , the Company closed its previously announced financing package for a total ofUS$50 million fromSprott Resource Streaming and Royalty Corp. and its affiliates (“SRSR”) andNebari Credit Fund II, LP (“Nebari Credit Fund II”), as described in the Company’s news release datedJanuary 22, 2024 .$13,700 of the above proceeds were used to buy back two existing 5% NSR royalties on various PGP property claims onMarch 15, 2024 . - On
February 20, 2024 , concurrently with the above-noted financing package, the Company closed its previously announced bought deal private placement financing, under which the Company issued a total of 65,343,000 common shares of the Company (the “Common Shares”) at a price of$0.44 per Common Share, for gross proceeds of$28,751 . - At the end of Q1 2024, overall construction excluding mine development was 98% complete compared with 86% complete at the end of 2023. A few remaining commissioning activities in the mill are underway. The tailing storage facility was completed and signed off by the engineer of record at the end of
March 2024 . - The new water treatment plant began operations in
February 2024 . The high-density sludge plant has been successfully commissioned and water is being treated and discharged into the environment. The moving bed bio-reactor (“MBBR”) is complete and media have been loaded into the tanks. - As of
April 30, 2024 , underground development totaled approximately 2,710 metres at Big Missouri and 150 metres at Premier.
DEVELOPMENT OF THE PROJECT
Project financing
On
Construction progress key performance indicators
At the end of Q1 2024, overall construction was 98% complete, compared with 86% complete at the end of Q4 2023. With first gold having been poured on
Safety
The Project had no lost time injuries in Q1 2024. There was an increase in recordable injuries at the end of the quarter which in part, can be attributable to seasonal changes and the transition from construction to operations. As the Project continues its transition from construction into operations, focus has been placed on the ongoing development of standard operating procedures, in field job hazard analysis and worker training. There was a small increase in property damage reported in the quarter due in part to weather conditions and the onboarding of a significant number of new workers to the site. The re-enforcement of reporting to the operating team remains a key focus to ensure that all learnings are identified and applied to prevent re-occurrence and reflect in the future training plans. In Q2 2024, significant work will be placed to support the operational teams to begin to operate the newly constructed plant through the final stages of C4 and C5 commissioning.
Processing plant and site infrastructure
Mechanical and electrical work in the mill was substantially completed in Q1 2024 with minor associated systems and punch list items to complete. Focus has shifted to commissioning the process plant and ramp up as well as completing minor deficiencies.
Stage one of the tailings storage facility (“TSF”) raise was completed and accepted by the Engineer of Record for use. Earthworks activities in 2024 will focus on raising the spillway dam by three metres, producing material for the 2025 raise and advanced work on the Cascade Creek Diversion in preparation for the 2025 works and final completion of the diversion.
The new water treatment plant was substantially mechanically and electrically completed in Q4 2023 with some minor areas remaining. The high-density sludge circuit was commissioned in Q1 2024 and is advancing towards full ramp up. The MBBR circuit was substantially complete in Q1 2024 and will begin full commissioning as the process plant continues to deposit tailings into the TSF and feed nitrogen species into the MBBR circuit.
The site power reticulation was completed in Q1 2024. Sustaining capital works in 2024 will focus on reticulation to the Premier portal as well as the Big Missouri portal.
Mine development
At Big Missouri,
During Q1 2024, the geological team continued to encounter high grade material occurrences in both face sampling and probe hole drilling in multiple areas of the A zone. As previously reported, these occurrences are in or very near existing wireframes or logical extensions of wireframes. At the end of
At PNL,
Mining development is being advanced down into the Premier deposit for initial mining in the
Recruitment
At the end of Q1 2024, total site recruitment has reached approximately 90% of the planned operational team. A key achievement was the successful recruitment for some challenging roles pertaining particularly to some of the maintenance roles, health and safety (specifically, mine rescue), and technical roles for the mine and processing area. Policies and procedures development have been ongoing throughout Q1 2024 and key documents will be rolled out in Q2 2024.
Permitting and Environmental Compliance
A Joint Permit Amendment Application (“JPAA”) was required to be re-aligned with the project completion dates and was submitted in
The air permit was received on
2024 EXPLORATION PROGRAM
Planning for the 2024 exploration program is in full swing with an anticipated start date in late June. There are several areas on the properties that will be targeted by new drilling. Near the Premier mill, several drill holes have been planned around the Prew and Sebakwe zones of the Premier deposit. The new holes will complement the existing drill pattern at Prew and test induced polarization geophysical anomalies from last year’s survey.
Additional drill holes have been planned for the Big Missouri deposit where underground development is rapidly providing access to different parts of the deposit. The new holes will be designed for resource conversion and mine plan addition at this deposit. Specific new drill targets have been identified at the
Additional exploration drill holes are targeting a large geophysical anomaly to the west of the Dilworth deposit that extends surface showings to the north onto Ascot’s PGP property. This target has a large strike extent and may require drilling over more than one exploration season.
The Company anticipates a drill program of between 15,000 and 20,000 metres distributed over the areas described above. The program will require utilization of two drill rigs into late September or early
FINANCIAL RESULTS FOR THE THREE MONTHS ENDED
The Company reported a net loss of
LIQUIDITY AND CAPITAL RESOURCES
As at
MANAGEMENT’S OUTLOOK FOR 2024
In 2024, the Company will transition from the construction of the mine and related infrastructure to the operation of the entire site and becoming a gold producer. Despite the challenges associated with this transition, there are many opportunities for the Company to grow and create value.
The key activities and priorities for 2024 include:
- Making health and safety a priority in the commencement of operations
- Completing the commissioning of the process plant
- Completing the access ramp and starting the mine production at the Premier deposit
- Continuing to expand the mine production and development at the Big Missouri deposit
- Shipping and selling of gold doré
- Advancing the exploration and infill drilling program on the numerous opportunities to increase resources
- Compliance with the environmental requirements of the site and making sure water treatment and the tailings management facility operate as designed
- Successfully transition from a mine developer to a mine operator
Qualified Person
On behalf of the Board of Directors of
“Derek C. White”
President & CEO, and Director
For further information contact:
VP,
dstewart@ascotgold.com
778-725-1060 ext. 1024
About
Ascot is a Canadian mining company focused on commissioning its 100%-owned
For more information about the Company, please refer to the Company’s profile on SEDAR+ at www.sedarplus.ca or visit the Company’s web site at www.ascotgold.com.
The TSX has not reviewed and does not accept responsibility for the adequacy or accuracy of this release.
Cautionary Statement Regarding Forward-Looking Information
All statements and other information contained in this press release about anticipated future events may constitute forward-looking information under Canadian securities laws ("forward-looking statements"). Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeted", "outlook", "on track" and "intend" and statements that an event or result "may", "will", "should", "could", “would” or "might" occur or be achieved and other similar expressions. All statements, other than statements of historical fact, included herein are forward-looking statements, including statements in respect of the terms of the Offering, the closing of the Offering, the advancement and development of the PGP and the timing related thereto, the completion of the PGP mine, the production of gold and management’s outlook for the remainder of 2024 and beyond. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements, including risks associated with entering into definitive agreements for the transactions described herein; fulfilling the conditions to closing of the transactions described herein, including the receipt of TSX approvals; the business of Ascot; risks related to exploration and potential development of Ascot's projects; business and economic conditions in the mining industry generally; fluctuations in commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; the need for cooperation of government agencies and indigenous groups in the exploration and development of Ascot’s properties and the issuance of required permits; the need to obtain additional financing to develop properties and uncertainty as to the availability and terms of future financing; the possibility of delay in exploration or development programs and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals; and other risk factors as detailed from time to time in Ascot's filings with Canadian securities regulators, available on Ascot's profile on SEDAR+ at www.sedarplus.ca including the Annual Information Form of the Company dated