A reheating furnace upgrade completed at El Masria Steel - part of Garhy Steel Group, near Cairo, Egypt, included a new combustion system, featuring field instrumentation, a new recuperator (energy recovery form waste gases) and a new automation system.

All existing burners for the preheating, heating and soaking zones were replaced with Daniel's original MAB -Multi Air Staging Burners, providing additional thermal capacity to achieve the target furnace productivity and operational flexibility.

The target of 25% fuel consumption saving was not only achieved but improved by a further 20%, resulting in both financial benefits -operational expenditure- and environmental impact -reduced CO2 emissions.

The outstanding performance led to an extremely quick final acceptance for the project.

Attachments

  • Original document
  • Permalink

Disclaimer

Danieli & C. Officine Meccaniche S.p.A. published this content on 26 March 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 26 March 2021 17:32:03 UTC.