Balfour Beatty, alongside EDF, has celebrated a major milestone on its Hinkley Point C tunnelling and marine project, as the team successfully completed the breakthrough of the longest and final onshore cooling-water tunnel, at the UK's landmark nuclear power station.

This momentous milestone marks the completion of Balfour Beatty's sprayed concrete lining works at Hinkley Point C; a well-established method for large diameter tunnel construction using mechanical excavation and the application of sprayed concrete to provide ground support.

Excavating through 600 metres of ground to create the tunnels, the team worked safely and swiftly to spray the ground with 9000m3 of concrete in order to stabilise the recently formed underground structures. In total, the process required over 1.6 million hours across the tunnels, with the programme of works completed to schedule.

The five onshore tunnels will now undergo secondary lining works, installing a number of reinforced rebar concrete structures to further stabilise the sprayed concrete.

In total, the team have successfully completed all five onshore tunnels which will play an essential role in the critical cooling water system for the nuclear power station, responsible for transferring over 120,000 litres of water per second to Hinkley Point C from the Bristol Channel.

The same team have prepared three portals to facilitate the launch of the Tunnel Boring Machines (TBM) which will excavate the tunnels for the main cooling water system. The first TBM has already set off on its journey, having travelled over 2.5 kilometres, 33 metres under the Bristol Channel.

Alistair Geddes, Balfour Beatty Project Director for Hinkley Point C's tunneling and marine project, said: 'This is a significant step forward in the successful delivery of the first new nuclear power station in the UK for over 20 years. Achieving this incredible milestone is testament to Balfour Beatty's unrivaled expertise in delivering projects of this scale and complexity.'

On completion, Hinkley Point C will supply safe, secure, low carbon electricity to around six million homes.

Balfour Beatty is contracted to three major packages of works at Hinkley Point C. It was first appointed to deliver the electrical package in a joint venture in 2015, the tunneling and marine package in 2017 and most recently the 400kV overhead line project on behalf of National Grid in 2019.

Image: Balfour Beatty breaks through at Hinkley Point C

ENDS

Media enquiries to:
Vivienne Dunn Balfour Beatty
+44 (0)203 810 2345
vivienne.dunn@balfourbeatty.com
www.balfourbeatty.com| follow us @balfourbeatty

All non-media related enquiries should be directed to +44 (0)20 7216 6800 orinfo@balfourbeatty.com

Notes to editors:

  • Balfour Beatty (com) is a leading international infrastructure group. With 26,000 employees, we provide innovative and efficient infrastructure that underpins our daily lives, supports communities and enables economic growth. We finance, develop, build and maintain complex infrastructure such as transportation, power and utility systems, social and commercial buildings.
  • Our main geographies are the UK, US and Hong Kong. Over the last 110 years we have created iconic buildings and infrastructure all over the world including the London Olympics' Aquatic Centre, Hong Kong's first Zero Carbon building, the National Museum of the Marine Corps in the US and the Channel Tunnel Rail Link.
  • Balfour Beatty's Major Projects business deliver large-scale, complex infrastructure projects which keep the UK moving and the economy thriving. Employing over 2,000 people, the business operates within three principal markets; Transportation; Energy and Power and Major Infrastructure.
  • To maximise our offering on major infrastructure projects, we partner with the world's leading international companies in joint ventures such as VINCI, Skanska and Mott MacDonald to complement our construction offering on mega-infrastructure projects.
  • Our current portfolio of major projects include two design and build contracts for High Speed 2 in a joint venture with VINCI, the four-year Hinkley Point C nuclear power station tunnelling and marine works package on behalf of EDF Energy and London's new major super-sewer through central London, in a joint venture with BAM Nuttall and Morgan Sindall.
  • Iconic projects of the past include Heathrow Airport Terminal 2 departure lounges, the transformation of the iconic former London Olympic Stadium into a multi-purpose sporting venue and in a joint venture with VINCI the South West of England's first Smart Motorway to improve journey safety and traffic capacity on the M4 and M5.

Attachments

  • Original document
  • Permalink

Disclaimer

Balfour Beatty plc published this content on 06 October 2020 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 06 October 2020 08:04:07 UTC