July 08, 2020

Enbridge has now submitted to the Michigan Circuit court and to the State the results of our inspection of the area of interest on the west segment of Line 5. A direct link to the report can be found below.

The inspection, using an inline inspection tool, found no internal or external metal loss or dents. This test reconfirms that the west leg of the pipeline is safe to operate.

Enbridge has throughout this period kept both the Pipeline and Hazardous Materials Safety Administration (PHMSA) and the State of Michigan fully advised of the status of the west and east segment investigations and will continue to do so.

We are committed to protecting the environment and the people who use the waters of the Great Lakes, while keeping energy flowing to those who need it.

Click here to see the full report.

Attachments

  • Original document
  • Permalink

Disclaimer

Enbridge Inc. published this content on 08 July 2020 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 09 July 2020 07:27:02 UTC